Drone aerial photo of the Eastern Freeway at Doncaster Road showing major construction works for the North East Link

September 2025 update on the North East Link

As construction of one of the world’s biggest road projects continues unabated, I have been doing my best to document its progress.

The $26 billion new North East Link tollway and associated widening of the existing Eastern Freeway is scheduled to be finished by 2028.

Its massive scale is difficult to overstate. The 10 kilometres of the North East Link itself is in addition to the project scope extending all the way along the entire length of the Eastern Freeway from Hoddle Street to Springvale Road, and the M80 Ring Road from Plenty Road to the Plenty River. It will more than double the width of the road reservation, in many places completely transforming the landscape and surrounding areas.

This photo taken from the bridge over the Eastern Freeway looking towards Bulleen Road gives you a taste of what I mean.

Looking east towards Bulleen Road over Eastern Freeway widening works as part of North East Link construction near Freeway Golf Course in North Balwyn, Melbourne

This is what the same area looked like in 2017.

Eastern Freeway from Bulleen Road overpass

A bit further along on the east side of Bulleen Road, we come across the first of many diversions and disruptions to the Koonung Creek Trail, the main cycling and walking route in this part of the world. I didn’t see a single other person on this section of the Trail when I was there on what was formerly a busy shared path.

Temporary diversion of Koonung Creek Trail during Eastern Freeway widening works as part of North East Link construction near Bulleen Road in North Balwyn, Melbourne

The detour takes you around a hairpin bend, down a narrow path and onto local streets.

Shared path diversion onto Highview Road from Koonung Creek Trail near Bulleen Road during Eastern Freeway widening works as part of North East Link construction in North Balwyn, Melbourne

In many cases, temporary 40km/h speed limits have been installed on detour routes. These have been accompanied by temporary traffic calming measures, including speed cushions and even mini-roundabouts.

Temporary 40km/h speed limit on Viewpoint Road on Koonung Creek Trail detour during Eastern Freeway widening works as part of North East Link construction in North Balwyn, Melbourne

I got a bit lost from here and went down the wrong path, ending up on Kosciusko Road (yes it is still spelled incorrectly).

Here there is a massive carpark and staging ground. The vast majority of what was once Koonung Creek Reserve, wetlands and bushland has been occupied by the construction area.

North East Link carpark and staging site in Koonung Creek Reserve in North Balwyn, Melbourne

There is so much traffic entering and exiting this area that they have installed a temporary raised priority crossing for the Trail at the driveway.

Temporary shared path priority crossing over driveway into North East Link carpark and staging site in Koonung Creek Reserve in North Balwyn, Melbourne

The further you travel east the more construction work you see.

Here is the view looking east from the Estelle Street Bridge along the Eastern Freeway in 2014.

Eastern Freeway

And here it is today.

Looking east along the Eastern Freeway from Estelle Street Bridge during North East Link construction works in North Balwyn, Melbourne

One thing you can see to the right of the 2025 photo is part of the new shared path bridge that is being built to replace the original Estelle Street Bridge on which I was standing.

Looking west from the bridge here you can see even more construction work, with the site more than double the existing width of the Eastern Freeway.

Looking west along the Eastern Freeway from Estelle Street Bridge during North East Link construction works in North Balwyn, Melbourne

Although I couldn’t get an exact photo from the same spot, this is where the wetlands and remnant grassland in the Reserve was located.

Koonung Creek wetlands
Former gravel path and former wetlands in Koonung Creek Reserve during North East Link construction works in North Balwyn, Melbourne

Approaching Greythorn Road is another major detour of the Koonung Creek Trail. As of April 2025, the underpass at Doncaster Road is closed. It is scheduled to be like this for at least 18 months.

The underpass itself has been filled with concrete. I’m unsure exactly why – perhaps something to do with its structure?

Koonung Creek Trail shared path underpass of Doncaster Road filled with concrete during North East Link construction works in North Balwyn, Melbourne

Further back is a temporary citybound on-ramp for the Eastern Freeway from Doncaster Road. This includes a bus stop (which now only services the 905 and 907) and a pedestrian crossing that can only be used by construction workers to access one of the site gates.

Temporary bus stop on Doncaster Road on Eastern Freeway On Ramp during North East Link construction works in North Balwyn, Melbourne

Other bus stops in the area remain closed and more are progressively being shut, making it an increasingly long walk for people to access public transport.

Disused westbound bus stop on Doncaster Road at Greythorn Road during North East Link construction works in North Balwyn, Melbourne

There is a lot more to see along all three roads but I will leave it there for now.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.